 Prometa Estimating Analysis
    Generally, during  the cost-checking process,if the  cost an element  differs  from the cost  plan, it will  be  necessary  to adjust  the cost of  other  elements that  make  a balance  or  perhaps  draw  on  reserves  set aside in  the cost plan . However, if  it is impossible  to keep within  the set  target,ProMeta must  report  this to the  designer  who may consider  a different  design solution  or accept the increased  cost as the part of value management .